From Tore Supra to WEST : Evolution of CODAC infrastructure

14 May 2019, 12:20
20m
Daejeon, Republic of Korea

Daejeon, Republic of Korea

Board: O/4-5
Oral (Plenary Session) Plasma Control Plenary Oral

Speaker

Mr Benjamin Santraine (French Alternative Energies and Atomic Energy Commission)

Description

Since 1988, the Tore Supra limiter tokamak at CEA Cadarache has been in operation, and obtained the record of the longest plasma duration of 6 minutes 30 seconds and over 1000 MJ of energy injected and extracted. In 2013 Tore Supra went through major changes to become the WEST tokamak (Tungsten Environment in Steady state Tokamak). The tokamak was upgraded into an X point divertor device. Taking advantage of its long discharge capability, WEST's goal is to minimize technological and operational risks of the actively cooled tungsten divertor for ITER.
Concerning data acquisition, the “Control, Data Access and Communication” (CODAC) system has been redesigned in order to satisfy the performance and evolutions needed by researchers. A new architecture has been developed and deployed on major plant systems all around the fusion reactor allowing to fulfill the performance requirements of acquisition units, and for greater maintainability.
This paper describes the WEST CODAC system created in 2013 and evolving since. The introduction briefly presents Tore Supra and the original CODAC based on VME technology. The main section exposes the upgrade of Tore Supra into WEST and the architecture evolution. The diskless Linux system and the attached PXI or VME systems are described with the tests realized for the CODAC system. During three WEST experimental campaigns, the new CODAC infrastructure ran over major plant systems like magnetics or power plant diagnostics. Results from those systems are shown in the last section leading to conclusion and prospects.
After two years of operation, three experimental campaigns and more than 4000 pulses, the WEST CODAC infrastructure has proven its efficiency and reliability, while the CODAC team still working on possible improvements.

Primary author

Alexandre Berne (CEA-IRFM, F-13108 Saint-Paul-lez-Durance, France)

Co-authors

Mr Benjamin Santraine (French Alternative Energies and Atomic Energy Commission) Mrs Nathalie RAVENEL (CEA-IRFM, F-13108 Saint-Paul-lez-Durance, France) Mr Julian COLNEL (CEA-IRFM, F-13108 Saint-Paul-lez-Durance, France) Mr Gilles CAULIER (CEA-IRFM, F-13108 Saint-Paul-lez-Durance, France) Mr Fabrice LEROUX (CEA-IRFM, F-13108 Saint-Paul-lez-Durance, France)